Taping, Mudding & Painting (hey - I don't make these names up).
Family room and fireplace getting taped
Roxanne inspects the garage drwall.
Living room completely taped.
Dining Room looking north.
Kitchen taped and mudded.
Media Room almost ready for Matrix and Star Wars Episode III
Rob's room
Tim mans the automatic gun (paint gun).  Notice the OSHA approved gear.
Partially painted garage.
Painted dining room.
Front entry way.
Painted family room.
Tim puts on final touches of Rob's closet.
Painted living room.
Flooring and Cabinet Installation (last week of October)
Rob's flooring goes in.
Roxanne installs living room flooring.
Rob's flooring installed.
Rob showing his flooring prowess....
Kitchen cabinets getting unboxed and placed.
Kitchen getting crowded!
First kitchen cabinet goes up Sunday, Oct 30th!
Rob's room is the first completed room in the house.
More wall cabinets getting installed.
Tile flooring and bathroom build-out.
Final Kitchen cabinet & appliance placement!

Finalized rooms...
Next - Move In!
Phase 5 - Final items!
OK - We have to get outta this office!  So, the plan is to
have temporary permit of occupancy by the end of
October.  Then we will tear down the garage and put our
belongings back into the house!
First room (living room) gets drywall!
Drywall!  2 days - start to finish for 3200 sq ft!
Living room is the first to get drywall!
Living Room completely drywalled!
Living room looking towards Dining Room
Garage is finally being emptied!
Hallway by Brooke's bath.
Master Bedroom
Master Bath
Master Closet & new gun safe (beware...)
Master Bed looking south
Brooke's bedroom
Spare Bedroom
Family and Dining room
Game / Media room!
Game / Media room take #2
Brooke's bath